Completed project · Western Siberia

Associated gas power facility

Associated gas power facility: detailed and cost documentation

  • Power
APG utilisation
100%
technical solutions for electricity metering
AMR

Per the reference list

Reference list
Role · period
General contractor · 2024 · completed on schedule
Region
Western Siberia

Per the reference list

Reference list
Facility
Associated gas power facility: technical solutions for electricity metering
Role · period
General contractor · 2024 · completed on schedule
Region
Western Siberia

Scope of work

  1. 01Development of detailed documentation
  2. 02Technical solutions for an automated commercial electricity metering system
  3. 03Noise impact calculation
  4. 04Noise mitigation measures
  5. 05Development of cost estimate documentation

Highlights

  • 100% APG utilisation
  • Use of the generated electricity at the field
  • Calculation of noise impact on personnel; the standard level is achieved through sound-absorbing measures